UPCOMING:
June 5, 2023 | Retrofit construction begins, south east corner, main and upper level.
IMPACTS:
- Construction noise
- North, South and EHSEB bridge entries all accessible

May 24, 2023 | Level A access to School of Medicine (SOM) closes. Concrete removal scheduled to start.
IMPACTS:
- Level 1 south east door opens with badge access
- Potential concrete removal begins anticipate high-level noise, ground vibrations and disruptive working environments
- North, South and EHSEB bridge entries all accessible

May 23, 2023 | North and South doors of EHSL replaced, main entrance closes
IMPACTS:
- North and South doors inaccessible
- Main entrance closes for duration of SOM construction
- EHSEB bridge entry remains open

May 23, 2023 | EHSL main and north entrance closed no card entrance. Access through the EHSEB bridge. Reopening TBA.
Due to a new doors and card reader installation at the new south entrance location.
May 22, 2023 | School of Medicine (SOM): West sidewalk closes
IMPACTS:
- Access to Main level entrance closed for duration of SOM construction
- EHSL access restricted to EHSEB bridge and North doors


May 11, 2023 | Phase 1: South bike racks removal
May 8, 2023 | Phase 1: Furniture removal from the southeast corner on the main level.
April 17, 2023 | Spencer Fox Eccles School of Medicine construction perimeter fence installation.
View the construction map for impacted areas.

Traffic Impacts

To see the most current information https://map.utah.edu/
March 16, 2023 | We have exciting news for 2023: EHSL is preparing for an earthquake retrofit! We anticipate construction changes and updates over the next three years. Stay up to date on all the details at the construction website.
View Seismic Construction Timeline